SPOKANE COUNTY, Wash. — Repaving work will cause some ramp closures on Highway 395 starting next week.
According to the Washington Department of Transportation, this project will repave about nine miles of the highway between Hatch Road and Hamilton Road.
The northbound on-ramp and southbound off-ramp at Hatch Road will close on Monday, September 23, from 8 p.m. to 6 a.m. It will close again during that same time frame on Thursday, September 26.
WSDOT said the southbound on-ramp and northbound off-ramp will be closed overnight on Tuesday, September 24 and Friday, September 27 as well.
All ramps on the highway will stay open between 6 a.m. and 8 p.m. Drivers can expect single-lane closures during daytime hours.
Speeds in the work zone will be reduced to 45 miles per hour until the work is complete.
For more on the project, click here.
COPYRIGHT 2024 BY KXLY. ALL RIGHTS RESERVED. THIS MATERIAL MAY NOT BE PUBLISHED, BROADCAST, REWRITTEN OR REDISTRIBUTED.